Honorable Mayor and Members of the Hermosa Beach City Council Regular Meeting of November 24, 2020
Title
CAPITAL IMPROVEMENT PROGRAM STATUS REPORT
AS OF NOVEMBER 17, 2020
(Public Works Director Marnell Gibson)
Body
Recommended Action:
Recommendation
Staff recommends that the City Council receive and file the Capital Improvement Program Status Report as of November 17, 2020.
Number of Projects/Studies by Phase
# of Projects/Studies
Study/Conceptual Planning
9
Preliminary Design
14
Final Engineering Design
11
Project Approvals/ Bidding
1
Construction
Closeout
2
Total Projects
31
Total Studies
7
Number of Projects/Studies by Completion Timeline
1 - Complete by end of FY 19-20
10
2 - Complete in FY 20-21
8
3 - 3 years to completion
0
4 - 5 years to completion
5 - TBD
18
Projects/Studies Complete
Number of Projects/Studies by Category
Street & Highway Improvements
Sewer & Storm Drain Improvements
6
Park Improvements
Public Building & Ground Improvements
20
Number of Projects/Studies by Manager
Lead
Support
Total
Lucho Rodriguez
Reed Salan
Romany Basilyous
Andrew Nguyen
Doug Krauss
3
Leeanne Singleton
Kelly Orta
TBD
12
Total Projects/Studies
38
Attachments:
Capital Improvement Program Status Report as of November 17, 2020.
Respectfully Submitted by: Marnell Gibson, Public Works Director
Approved: Suja Lowenthal, City Manager