Staff recommends that the City Council receive and file the Capital Improvement Program Status Report as of September 10, 2020.
Number of Projects/Studies by Phase
# of Projects/Studies
Study/Conceptual Planning
6
Preliminary Design
17
Final Engineering Design
12
Project Approvals/ Bidding
1
Construction
Closeout
Total Projects
31
Total Studies
7
Number of Projects/Studies by Completion Timeline
1 - Complete by end of FY 19-20
2 - Complete in FY 20-21
4
3 - 3 years to completion
0
4 - 5 years to completion
5 - TBD
21
Projects/Studies Complete
Number of Projects/Studies by Category
Street & Highway Improvements
10
Sewer & Storm Drain Improvements
Park Improvements
2
Public Building & Ground Improvements
20
Number of Projects/Studies by Manager
Lead
Support
Total
Lucho Rodriguez
Reed Salan
Romany Basilyous
Andrew Nguyen
8
Doug Krauss
3
Leeanne Singleton
Kelly Orta
TBD
16
Total Projects/Studies
38